PROJECT AUTHORIZATION | PACKET ID: PMT-8T2Q |
CONTRACT ID | EMARS PROGRAM CODE | AUTHORIZATION NO: | |
1605801D | 16056 | 0 | |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID | PROJECT ID NUMBER | FEDERAL PROJECT NUMBER | 6 YR PLAN ITEM NUMBER | 6 YR PLAN ITEM PARENT NUMBER |
053 005 1 007-009 |
STP 0051051 |
01-80203 |
PROJECT TYPE | PROJECT LENGTH | NUMBER OF BRIDGES | SYSTEMS |
PAVE RECON W/ALIGN | 1.0110 |
PROJECT PHASE & RESPONSIBILITY |
PLANNING | DESIGN | RIGHT OF WAY | UTILITIES |
CONSTRUCTION | TITLE DEEDED TO: | MAINTENANCE | OTHER | |
FUNDING & TIME ACCOUNTABILITY |
PARTICIPATING AGENCIES | |||||||
FEDERAL | STATE | LOCAL | OTHER |
ITEM NUMBER | PHASE | FUND | PROGRAM | FEDERAL FISCAL YEAR | STATE FISCAL YEAR |
||
FEDERAL APPR CODE |
CURRENT FUNDING REQUEST | ||||||
1-80203 | D | 1200 | FD52 | 2023 | 2023 | Y238 | $800,000.00 |
1-80203 | D | 1100 | FD52 | 2023 | 2023 | Y238 | $200,000.00 |
CURRENT FUNDING REQUEST TOTAL: $1,000,000.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE | TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING | $0.00 |
DESIGN | $1,000,000.00 |
UTILITIES | $0.00 |
R/W | $0.00 |
CONSTRUCTION | $0.00 |
NON-HIGHWAYS | $0.00 |
Total: $1,000,000.00 |
REMARKS: | THIS AUTHORIZATION PROVIDES FD52 STP FUNDS WITH STATE MATCHING FUNDS FOR PE & ENVIRONMENTAL. |
Project Approval Recommended By: James Ballinger 12/27/2022 |
Signed and Approved by: Jim Gray 12/27/2022 |
AUTHORIZATION LOCATION | ||||||
ITEM NO. | COUNTY | DIST | FACILITY NAME |
ROUTE | LENGTH | SCOPE |
01-80203.00 | HICKMAN
|
1 | US-51 S S WASHINGTON ST N WASH | US 51 | 1.0110 | Correct geometric deficiencies and improve safety, access, and regional connectivity from Clayton Street to KY-703 in Clinton. (2022CCN) |